Glasgow School of Art Directors Newsletter contains an important update regarding the progress of the new campus. You can read the whole newsletter via that link back there, but the relevant excerpt reads as follows:
“…the contractor, Sir Robert McAlpine, is now in a position to give a more definitive date for handover of the building: 27th September 2013. This is slightly later than originally anticipated because of problems at the demolition stage caused by more extensive asbestos being discovered in the Newbery Tower than had been identified in the survey and obstructive piling under the Newbery Tower which had not been recorded in the Tower building plans.
This means that we will not fully occupy the Phase 1 building until January 2014 and staff and students will remain at Skypark for Term 1 of academic year 2013-14.
In preparation, a Migration Working Group has been established to lead on the planning for relocation of students, staff and facilities from Skypark to Garnethill, the occupation of the new building and the wider impact which the later handover date may have on staff and students based in Garnethill. Once the Group has progressed the initial planning we will issue an email to students and staff to update them.”
0 Responses to “Com Des and Skypark”